Job Progress & 12-Week Cash Forecast — DEMO (anonymized sample data)
Scheduled receipts by time bucket
Weekly — next 12 weeks (ending Friday)
Monthly — next 6 months
| Date | Day | Customer | Job | PM | Description | Amount | When |
|---|
| Amount | Job # | Customer | PM | Bill | Collect |
|---|
Each row is one cash milestone, pairing its Bill and Collect legs. Status: ✓ done (checked in JobTread), → in progress (a Bill due today, or a Collect within 2 days of its bill), ✕ past due (a Bill past its date, or a Collect more than 2 days past its bill), ● not yet scheduled / future. A no collect tag marks a Bill with no matching Collect scheduled — a gap to review. Amounts shown once per milestone.
| Customer | Job | PM | Phase | Next Scheduled Event | Remaining Scheduled Cash | Last Scheduled Date |
|---|
Active = job has at least one open task and its Start of Work milestone (or first materials payment) is already behind us. Phase reflects construction progress: Framing — work has started but the drywall / midpoint bill has not gone out yet; Finish Work — the drywall (or halfway/midpoint) milestone has been billed, taken as any drywall leg (bill or collect) dated on or before today, since a scheduled collect implies the bill issued; Punch Out — approaching final billing, with only Punch Out / final cash still ahead. Remaining cash is the post-dedup forecast for that job (unknown-$ events excluded from the figure, counted separately).
| Projected Start | Customer | Job | On Track | 10% Deposit | Finish Materials | Start of Work Bill | Remaining |
|---|
A ✓ marks a milestone whose Collect leg is already behind us (treated as collected). 10% Deposit and Finish Materials show the scheduled draw; Start of Work Bill is the trigger amount that opens construction; Remaining = job value − cash already collected. On Track reflects the job's pre-construction (Measure / Design) progress from the Pre-Cons Ops view: On track if its design phases are progressing as scheduled, Behind if a phase window has closed without the next starting. The total row sums total job value across all pre-construction jobs.
Pre-Construction Progress — Measure & Design Schedule
Phase-by-phase status
| Customer | Job | Current Phase | Measure | Drawing Design | Materials Design | Status | Next cash milestone |
|---|
Each pre-construction job moves through Measure → Drawing Design → Materials Design before materials can be ordered and Start-of-Work can bill. Each row has two lanes: the Plan lane (top, hatched) shows the originally scheduled phase windows, and the Actual lane (bottom, solid) fills in once the designer logs actual start and end dates in JobTread — until then it shows a dashed placeholder. The vertical marker is today. A planned phase whose window has closed without the next starting is outlined in red. Next cash milestone shows the upcoming collection that follows once each job clears its design phases. Jobs without a scheduled design sequence in the export show —.
Material-order & cash readiness
| Projected Start | Customer | Job | Materials Order Status | Finish Materials $ | Start of Work $ |
|---|
Permitting Lens
This lens will track Permit — Submitted and Permit — Approved per job once a permitting export is supplied. The current export carries no permit status fields. Structure below is wired and ready to populate.
| Customer | Job | Permit Submitted | Permit Approved |
|---|
| Scenario | What it stresses | Baseline (12-wk) | Stressed | Δ | Risk |
|---|
Baseline = the as-built 12-week parseable forecast. Each scenario perturbs one assumption and re-totals cash landing inside the 12-week window. Risk reflects both the size of the swing and how plausible the scenario is for this client. This is a what-if lens for Tim — it shows what we started with and what survives stress, not a revised forecast of record.